The Bridges and Roads Authority issued a statement on Friday morning to announce that construction work of the Frisange slip road will be completed over the weekend.
The opening of the slip road brings an 18-year-long dispute to a conclusion.
Reason for the continued delay of the construction was the respective land owner's unwillingness to sell part of his property to the State. Following a court ruling in April, construction work was finally able to begin in mid May.
©
Domingos Oliveira
©
Domingos Oliveira
©
Domingos Oliveira
Sou huet d'Opfaart Fréiseng nach Ugangs 2022 ausgesinn. D'nächst Woch soll se endlech fir den Trafic opgoen. / ©
Domingos Oliveira / RTL
Situatioun Mëtt Abrëll 2022 / ©
Christophe Hochard
Fotoe vum Abrëll 2022 / ©
Domingos Oliveira / RTL
©
Domingos Oliveira / RTL
©
Domingos Oliveira / RTL
The photos published on this site are subject to copyright and may not be copied, modified, or sold without the prior permission of the owner of the site in question.
The new A13 slip road opened for traffic at 6am on Monday morning.