On A30 and A31Months of construction ahead on cross-border route

RTL Today
Motorists travelling between Metz and Thionville should brace for months of disruptions as major renovation work begins on the A31 motorway.
Ce pont de l'A31, situé juste avant le triangle de la Fensch et enjambant l'Orne, va être en travaux durant plusieurs mois.
Ce pont de l’A31, situé juste avant le triangle de la Fensch et enjambant l’Orne, va être en travaux durant plusieurs mois.
© Maurice Fick / RTL

The project, which focuses on a bridge spanning the Orne River near Richemont, will last five months, causing multiple road closures. The nearby A30 will also be affected.

According to DIR Est, the bridge – located just before the Fensch Triangle – is in poor condition. Issues include damaged road joints, a faulty waterproofing system, and worn-out bearings. To address these, an extensive repair project is planned, with additional minor works carried out simultaneously.

Le pont situé près de Richemont, au sud de la jonction A30/A31, va faire l'objet de longs travaux.
Le pont situé près de Richemont, au sud de la jonction A30/A31, va faire l’objet de longs travaux.
© DIR Est

Three phases of construction

The work will be carried out in three stages:

  • Phase 1 (17 March – mid-July): Work will take place beneath the bridge in both traffic directions, requiring around ten overnight closures of the A31.
  • Phase 2 (from 21 May, for six weeks): Repairs will focus on the southbound lanes, with 10 night closures and two full weekend closures (currently planned for 14-16 June and 21-23 June).
  • Phase 3 (from 23 June, for one month): The final phase will target the northbound lanes, requiring 15 night closures and one weekend closure (expected 12-14 July).

How will traffic be affected?

Despite the closures, DIR Est assures that daytime traffic on the A31 will remain mostly unaffected. However, overnight closures and weekend disruptions will be unavoidable:

During Phase 2: The A31 will be fully closed between Mondelange and Bertrange. The A30 will be blocked from the Uckange interchange.

Les déviations prévues lors des coupures d'autoroute de la phase 2.
Les déviations prévues lors des coupures d’autoroute de la phase 2.
© DIR Est

Weekend closures will extend the blockages from Bertrange to the Croix de Hauconcourt on the A31, and from Uckange on the A30.

La coupure des autoroutes A30 et A31 en phase 3.
La coupure des autoroutes A30 et A31 en phase 3.
© DIR Est

Diversions will direct traffic via the RN52 or RD1, running parallel to the motorway.

Les déviations obligatoires prévues en phase 2, lorsque l'autoroute A31 sera barrée le week-end.
Les déviations obligatoires prévues en phase 2, lorsque l’autoroute A31 sera barrée le week-end.
© DIR Est

During Phase 3: The A31 will again be closed between Bertrange and Mondelange.

The A30 will be blocked from Fameck to Mondelange. A weekend closure in July will extend the shutdowns further.

Les déviations obligatoires lors de la coupure de l'autoroute en juillet 2025, lors de la phase 3.
Les déviations obligatoires lors de la coupure de l’autoroute en juillet 2025, lors de la phase 3.
© DIR Est

Overnight closures will generally run from 9pm to 5am. DIR Est will provide updated schedules closer to the affected dates.