Besides the impact of the coronavirus crisis, there are also other factors which caused delays. In his answer, Bausch points out that the energy concept was amended, and the design of the school's workshops adjusted.
The minister stressed that everything is being done to complete the project by September 2021. Bausch suggested that the move from Ettelbruck to Gilsdorf could be done in several stages.