Esch-sur-Alzette roadworksMunicipality releases construction schedule for Boulevard G.D. Charlotte

RTL Today
Construction on Boulevard Grande-Duchesse Charlotte in Esch has been ongoing for years. The municipality has recently provided an update on the next phases of the project, with further small works set to be completed by mid-September.
© Pierre Weimerskirch (Archiv)

In a letter to residents, the municipality of Esch detailed the upcoming schedule:

25 July: The southern part of the intersection between Boulevard Charlotte and Avenue de la Paix will reopen, coinciding with the start of the collective leave on 26 July, which will last until 19 August.

26 July - 2 September: The northern part of the intersection will be completed and reopened. During this period, Rue de Rue de Mondercange, which has remained open, will be closed to facilitate the connection to the Lallange district.

Week of 9 September: The final asphalt layer will be laid.

PDF: Communication by municipality (in French)